Reorder Point in 7 Minutes

EOQ tells you how much to order. The reorder point tells you when. It is the inventory level at which you place a new order so the delivery arrives just as stock runs out. With steady demand, it is simply daily demand times the lead time.

Quick lesson

Reorder point explained simply

The reorder point is the stock level at which you place a new order so it arrives just as you run out: ROP = daily demand × lead time. In the example, 40 units a day and a 5-day lead time give a reorder point of 200 units.

What this reorder point lesson covers

  • What the reorder point is and how it differs from EOQ
  • What lead time and lead time demand mean
  • How to calculate the reorder point with steady demand
  • How to keep units consistent between demand and lead time

Reorder point formula, explained

Reorder point (no safety stock)
ROP = d × L
d
average demand per day (or per week)
L
lead time in the same time units
Daily demand from annual demand
d = Annual demand ÷ Working days per year
Working days per year
number of days the business operates

How to calculate the reorder point step by step (worked example)

A shop sells 40 units a day, and the supplier takes 5 days to deliver after an order is placed. At what inventory level should the shop reorder?

  1. Daily demand d = 40 units.
  2. Lead time L = 5 days.
  3. ROP = 40 × 5 = 200 units.
  4. When stock falls to 200, place the order; it arrives just as stock hits zero.

Answer: Reorder when inventory drops to 200 units.

EOQ vs reorder point

EOQReorder point
AnswersHow much to orderWhen to order
Based onDemand, ordering cost, holding costDaily demand and lead time
In the related examples500 units200 units

Harder reorder point questions

What if the lead time grows to 7 days?

ROP = 40 × 7 = 280 units. Longer lead times mean ordering earlier.

How do you get daily demand from annual demand?

Divide by working days, not calendar days, if the shop only sells on working days. For example, 10,000 units over 250 working days is 40 a day.

Common reorder point questions

What is the formula for reorder point?

With steady demand and no safety stock, the reorder point equals average demand per period multiplied by the lead time in the same periods. If demand is uncertain, add safety stock on top of that lead time demand.

What is lead time demand?

Lead time demand is how many units you expect to sell between placing an order and receiving it. It equals demand per day times lead time in days, and it is the core of the reorder point.

What is the difference between EOQ and reorder point?

EOQ answers how much to order each time. The reorder point answers when to place the order. They are used together: when stock falls to the reorder point, you place an order of EOQ units.

How do you find daily demand from annual demand?

Divide annual demand by the number of days the business operates in a year. For example, 12,000 units over 300 working days is 40 units a day. Check which day count the question uses.